Regional development projects with low expenditure against revised allocations in FY2017. Spending execution does not directly measure physical completion. IQD thousands.
Under review — 1 cell carries two readings. Originally transcribed in two passes and compared cell by cell; printed totals were checked where available. Agreement between passes does not guarantee a correct reading. Source review has corrected transcription errors; unresolved readings remain marked. The 2025 report includes earlier financial years and dated observations, not a current account of every institution. Neither contested reading is included in a computed total.
Ranked · Of budget · per cent
The lowest execution is 2% of the allocation, on a project in Diwaniyah Governorate.
Showing the lowest 12 of 27; every row is in the table below. Names in Arabic are the Board’s own; English renderings are added as the desk verifies them.
| Governorate where the project is | Project the project as the Board names it | Allowed the revised allocation | Spent what was actually spent | Of budget spend as a share of the allocation — low means the money mostly sat |
|---|---|---|---|---|
Anbarمحافظة الانبار | تجهز اليات تخصصية لبلدية الرمادي/الفلوجة | 9,000,000 | 5,000,000 | 56% |
Najaf Governorateمحافظة النجف لاشرف | انشاء (500) دار سكني واطئة الكلفة في منطقة مظلوم | 2,337,200 | 1,214,726 | 52% |
Najaf Governorateمحافظة النجف لاشرف | انشاء الطريق القوسي المرحلة الخامسة | 5,764,900 | 2,714,763 | 47% |
Wasit Governorate |
FEDERAL BOARD OF SUPREME AUDIT · ANNUAL REPORT 2025 · Printed page 64 · UNIT IQD k · CSV ↓
Originally transcribed in two passes and compared cell by cell; printed totals were checked where available. Agreement between passes does not guarantee a correct reading. Source review has corrected transcription errors; unresolved readings remain marked. The 2025 report includes earlier financial years and dated observations, not a current account of every institution. English names are the desk’s renderings; the Arabic is authoritative. Dollar equivalents are illustrative at a fixed IQD 1,500/$ reference (CBI purchases from the Finance Ministry under Cabinet Resolution 544, effective 7 October 2026; 1,300 before that date). This is not the historical exchange rate for the audited fiscal year, a market quote, or the rate offered to bank customers. Download the CSV · All tables
Source: the 713-page report copy used for these tables · FBSA annual-report archive ↗. The archived copy is identified by SHA-256 d73671625d4f… . On 5 October 2026, the official archive required a security check, so a fresh copy could not be compared with this registered edition. References open this edition at the PDF page; annex numbering restarts at 1. The illustrative conversion reference is documented in the CBI circular of 8 February 2023.
تسديد حسابات مشاريع منجزة لسنة/2016 |
5,150,960 |
2,413,713 |
47% |
Kirkukمحافظة كركوك | بناء (36) مدرسة ابتدائية سعة (6) صف | 107,400 | 42,800 | 40% |
Babil Governorateمحافظة بابل | انشاء متنزهات عدد (29) في عموم المحافظة | 23,890 | 8,966 | 38% |
Babil Governorateمحافظة بابل | استكمالات المشاريع للمحافظة | 899,548 | 320,050 | 36% |
Wasit Governorateمحافظة واسط | تطوير احياء سكنية بالخدمات الاساسية | 2,814,300 | 1,003,017 | 36% |
Kirkukمحافظة كركوك | بناء روضة اطفال في منطقة الفيلق | 60,600 | 21,100 | 35% |
Basra Governorateمحافظة البصرة | تجهيز ونصب وحدة معالجة عدد (2) طاقة | 119,900 | 40,000 | 33% |
Diwaniyah Governorateمحافظة الديوانية | تاهيل الشبكة الكهربائية للاحياء | 1,688,500 | 563,400 | 33% |
Basra Governorateمحافظة البصرة | هدم روضة عبد الله الرضيع وبناء روضة نموذجية | 574,900 | 173,000 | 30% |
Najaf Governorateمحافظة النجف لاشرف | بناء مدارس ابتدائية وثانوية سعة (12) صف مع القاعة | 1,443,500 | 424,848 | 29% |
Diwaniyah Governorateمحافظة الديوانية | تسديد حسابات مشاريع منجزة | 2,328,200 | 380,042 | 16% |
Dhi Qar Governorateمحافظة ذي قار | انشاء شوارع في الدور والمناطق المجاورة | 337,700 | 50,991 | 15% |
Kirkukمحافظة كركوك | تنفيذ شبكات مجاري مياه الصرف الصحي | 13,835,500 | 2,138,180 | 15% |
Kirkukمحافظة كركوك | بناء (27) مدرسة ابتدائية (18) صف | 607,800 | 82,343 | 14% |
Karbala Governorateمحافظة كربلاء | انشاء ابنية سايلو كربلاء (المركز) | 813,300 | 104,888 | 13% |
Diyala Governorateمحافظة ديالي | تبليط وترصيف ومجاري محلة (305) حي العمال | 1,452,100 | 135,121 | 9% |
Baghdadمحافظة بغداد | بناء مدارس مختلفة (18/12/6) عدد (13) | 1,684,200 | 123,565 | 7% |
Diyala Governorateمحافظة ديالي | بناء (24) مدرسة ابتدائية سعة (18) صف | 1,460,900 | 101,985 | 7% |
Diyala Governorateمحافظة ديالي | انشاء الممر الثاني سيطرة كنعان الي مدخل بلد روز | 5,392,600 | 274,130 | 5% |
Karbala Governorateمحافظة كربلاء | انشاء وتبليط طرق ريفية في الاقضية والنواحي | 1,851,300 | 87,898 | 5% |
Karbala Governorateمحافظة كربلاء | تبليط وتطوير شوارع في مركز المحافظة | 3,680,900 | TWO READINGS198,6771,986,777 | 5% |
Baghdadمحافظة بغداد | انشاء شبكات المجاري والصرف الصحي في المحمودية والمدائن وجسر ديالي والطارمية | 18,693,722 | 643,742 | 3% |
Dhi Qar Governorateمحافظة ذي قار | انشاء شوارع وارصفة في مركز المحافظة | 9,313,200 | 300,254 | 3% |
Diwaniyah Governorateمحافظة الديوانية | تنفيذ الشبكات الكهربائية لمختلف الاقضية والنواحي | 697,800 | 15,739 | 2% |