Project details FY2025
The table lists three projects, their companies, contract and start dates, execution periods, and direct delay periods. First extraction failed verification; the configuration was corrected and the table re-verified against the printed page — the failed attempt stays on record.
Under review — 2 cells carry two readings. Every figure in this table was transcribed twice, independently, from the printed page. Where the two transcriptions agree, the figure is published as verified. Where they disagree, BOTH readings are shown under a “two readings” mark — neither is presented as fact — until a human re-reads the printed page and settles it. Rows the two transcriptions could not match are withheld entirely. Disagreement is disclosed, never resolved by a model.
| Project | Company | Contract date | Column 4 | Column 5 | Direct delay duration |
|---|---|---|---|---|---|
بناء مدرسة ابتدائية 12 صف علي القطعة المرقمة 46/1/7م الطويل الغربي في قضاء الزبيدية | 12-20-20-2020-في | 400 | 2022/21/12 | 12 | |
| TWO READINGSبناء مدرسة ثانوية 18 صف مع قاعة مع مختبرات علي القطعة المرقمة 2/7788م38الخاجية k15بناء مدرسة ثانوية 18 صف مع قاعة مع مختبرات علي القطعة المرقمة 2/7788م38الخاجيةk15 | شركة الاكتاف | 2021/29/12 | 20 | 2022/28/9 | 9 |
| TWO READINGSمدرسة ابتدائية 12 صف علي القطعة المرقمة 61/1م ام هليل في قضاء الكوت k16مدرسة ابتدائية 12 صف علي القطعة المرقمة 61/1م ام هليل في قضاء الكوتk16 | شركة اعالي التقنية | 2021/29/12 | 20 | 2022/28/9 | 9 |
FEDERAL BOARD OF SUPREME AUDIT · ANNUAL REPORT 2025 · PRINTED PAGE 539 · UNIT none · CSV ↓
- Project
- Company
- Contract date
- Column 4
- Column 5
- Direct delay duration
Transcribed in two independent passes, cell-compared, reconciled against the printed total on page 539; a mismatch would have kept this table off the site. English names are the desk’s renderings; the Arabic is the Board’s own text and the authoritative version. Dollars at the official 1,300 IQD/USD budget rate, context only. Download the CSV · All tables