The table lists two contracts for completing the new customs crossing, including their amounts, dates, duration, project names, and planned and actual completion rates. Figures in IQD. First extraction failed verification; the configuration was corrected and the table re-verified against the printed page — the failed attempt stays on record.
| Contract no. & date | Company | Project | Award amount (IQD) | Contract duration (days) | Column 6 | Completion date after extensions | Planned completion rate (%) | Actual completion rate (%) |
|---|---|---|---|---|---|---|---|---|
5-9-29-2024-2024-في | ارض العمد للمقاولات العامة | تنفيذ المتبقي من اعمال مبني المسافرين | 27,998,539,500 | 180 | 2024/10/6 | 2024/12/9 | 58 | 25.5 |
5-10-29-2024-2024-في | ارض العمد للمقاولات العامة | تنفيذ اعمال الجانب التجاري بصيغة (تصميم وتنفيذ) | 33,000,000,000 | 540 | 2024/14/6 | 2024/12/6 | 34 | 0 |
FEDERAL BOARD OF SUPREME AUDIT · ANNUAL REPORT 2025 · Printed page 543 · UNIT IQD · CSV ↓
Originally transcribed in two passes and compared cell by cell; printed totals were checked where available. Agreement between passes does not guarantee a correct reading. Source review has corrected transcription errors; unresolved readings remain marked. The 2025 report includes earlier financial years and dated observations, not a current account of every institution. English names are the desk’s renderings; the Arabic is authoritative. Dollar equivalents are illustrative at a fixed IQD 1,500/$ reference (CBI purchases from the Finance Ministry under Cabinet Resolution 544, effective 7 October 2026; 1,300 before that date). This is not the historical exchange rate for the audited fiscal year, a market quote, or the rate offered to bank customers. Download the CSV · All tables
Source: the 713-page report copy used for these tables · FBSA annual-report archive ↗. The archived copy is identified by SHA-256 d73671625d4f… . On 5 October 2026, the official archive required a security check, so a fresh copy could not be compared with this registered edition. References open this edition at the PDF page; annex numbering restarts at 1. The illustrative conversion reference is documented in the CBI circular of 8 February 2023.