Bridge construction contract fines FY2025
The table shows the contract and actual completion dates, the delay duration, and the daily and total fines. Figures in IQD thousands.
| Contractual completion date | Actual completion date | Delay duration (days) | Daily penalty (IQD thousands) | Total penalty amount (IQD thousands) |
|---|---|---|---|---|
2023/28/12 | 2024/27/5 | 151 | 17,417 | 2,629,967 |
FEDERAL BOARD OF SUPREME AUDIT · ANNUAL REPORT 2025 · PRINTED PAGE 461 · UNIT IQD k · CSV ↓
Reading the columns
- Contractual completion date
- Actual completion date
- Delay duration (days)
- Daily penalty (IQD thousands)
- Total penalty amount (IQD thousands)
Transcribed in two independent passes, cell-compared, reconciled against the printed total on page 461; a mismatch would have kept this table off the site. English names are the desk’s renderings; the Arabic is the Board’s own text and the authoritative version. Dollars at the official 1,300 IQD/USD budget rate, context only. Download the CSV · All tables