Original contracts and delay periods FY2025
The table lists two original contracts, their key dates, and the delay period after the initial 30-day period.
| No. | Contract no. | Column 3 | Guarantee letter receipt date | Column 5 | Delay period after 30-day grace (days) |
|---|---|---|---|---|---|
| 1 | 05-21-2013-2151-العقد-QR | 2013/13/5 | 2013/9/7 | 2013/14/10 | 67 |
| 2 | 28-2014-2151-العقد | 2014/30/10 | 2014/12/3 | 2015/15/2 | 44 |
FEDERAL BOARD OF SUPREME AUDIT · ANNUAL REPORT 2025 · PRINTED PAGE 29 · UNIT none · CSV ↓
Reading the columns
- No.
- Contract no.
- Column 3
- Guarantee letter receipt date
- Column 5
- Delay period after 30-day grace (days)
Transcribed in two independent passes, cell-compared, reconciled against the printed total on page 29; a mismatch would have kept this table off the site. English names are the desk’s renderings; the Arabic is the Board’s own text and the authoritative version. Dollars at the official 1,300 IQD/USD budget rate, context only. Download the CSV · All tables